July 2021 Mill Report

posted in: Uncategorized | 0

This month was the planned ending date for the structural work by Ed Blaiklock.  His work ended more abruptly when extensive rot, previously unseen, was discovered in major support timbers in the west wall and roof.  He had other clients … Continued

May 2021 Mill Report

posted in: Uncategorized | 0

Work is still progressing smoothly.  Ed Blaiklock and Audra Ziobro are still there working on replacing rotten timbers and straightening the building.  They are doing a wonderful job and we are lucky to have them for such an extended period … Continued

April Mill Report

posted in: Uncategorized | 0

A short report does not mean little is going on.  Our carpenters, Ed and Audra, are plugging away efficiently.  They have worked their way around the building replacing rotten timbers as they go.  Then they got to the back (west) … Continued

March Mill Report

posted in: Uncategorized | 0

The structural work on the mill building itself continues with no big problems.  The walls of the main building are jacked up and some sills have been replaced.  The shed-roofed part on the right (north) side has been straightened and … Continued